October 21, 2025 12:00 PM
Elizabethtown Gas Pipeline Replacement Project Underway
Elizabethtown Gas Pipeline Replacement Project Begins Today – November 3, 2025
Elizabethtown Gas will begin a pipeline replacement and upgrade project to enhance safety and reliability in your neighborhood.
Streets Directly Affected:
Carter Terrace
College View Drive
Deerfield Drive
Ferris Place
Kenneth Lane
Mountain View Drive
Nancy Lane
Pleasant View Road
Seymour Road
🔧 What’s Happening:
Replacing aging natural gas mains with new, durable plastic pipes
Moving gas meters from inside homes to the outside
Replacing service lines from the gas main in the street to each home
Traffic & Work Hours:
Road closures will occur, but local traffic, school buses, etc. will have access through the work zones as needed.
Work hours: Monday–Friday, 7:00 a.m. to 3:30/4:00 p.m.
Final Restoration:
After the 2025–26 school year is completed and before August 21, 2026.
Questions or Concerns?
Hotline: 866-767-5558
Email: etgprojects@sjindustries.com
More info: elizabethtowngas.com/neighborhood
Thank you for your patience as Elizabethtown Gas works to safely modernize our community’s energy infrastructure.